Case Studies.
Q1.) A software
consultancy proposes to establish an installation for its computer environment
like-
One server
and 20 workstation.40 person in
the IT deptWork is
related to the s/w development.Setup will be
in heavy use approximately. (20 hours all 7 days)An area of
2000 sq ft is earmarked for the installation in a new building where the above
setup is implemented.As an IT
professional working for the company you are required to prepare a report for
advising the management about the required design, physical layout and other
necessary equipments for the proposed setup.
1. Write the steps for recruiting IT
persons.
2. If you have been asked to estimate the
cost for student admission and examination system for a typical college, what
technique you would use in doing so. Discuss other techniques with suitable
illustration.
3. Discuss the procedure of recruiting
DBA in the organization
4. Raj stationery Pvt ltd has been operating
computerized sales order processing system developed in Oracle, Since last Five
years
5. ABC co. has been operating
computerized sales order processing system developed which accepts enquires as
well as orders form customer through the web. Being the consultant appointed by
the Management you are required to develop Software Change Specification to be
made in the current software.
6. Mr. Navin Agarwal has given his
resignation, who was working in the well established organization, as a system
administrator, Management wants to take the expert opinion from you to support
this decision Suggest necessary precaution and controls to be exercised to do
so.
7. If you are asked to developed
software, which needs to satisfy some quality parameters
8. What steps you need to follow in doing
so, Describe the processes through which software quality can be assured.
9. If you were asked as an expert to
provide an estimate of the effort needed to make certain change to an existing
piece of software what information would you like to have to assist you in
making the estimate.
10. You have been entrusted with the
responsibility of setting up a modern state of architecture laboratory for your
college. List down the parameters required for planning of the site.
11. A public library dept. is considering
the implementation of a computer based system to administrator book loans at
libraries. What might be the objectives of such a project and how might the
success of the project be measured in the practical terms.
12. You have been appointed as a
consultant to estimate the cost of the software being developed for billing
system, suggest the suitable technique being used in doing so. Discuss why
other technique does not suit with your technical requirements. State
assumption if necessary.
13. Discuss the various factors are
considered in the planning of I.T Site.
14. Identify the action that could prevent
each of the following risks form materialization or could reduce the impact if
did occur.
A) A key member of the programming team
leaves.
B) Introducing a new version of the
operating system that has errors in it.
C) A disk containing copies of the most
up to date version of the software under development being corrupted.
D) System testing unearthing more errors
than expected and taking longer than planned